91社区 has mandated Corenov Constructeurs to carry out the following project: Macdonald Stewart Building (Macdonald Campus) / 20-021 JELF Roy.

The project consists of the renovation of lab MS2-094A on the second floor of the Macdonald Stewart Building.

Project manager:听Mark Ouimet 鈥撎mark.ouimet [at] mcgill.ca

Assistant project manager: Claudia Carpanzano听-听Claudia.carpanzano [at] mcgill.ca

Classified as: Macdonald Campus, Macdonald Stewart Building
Published on: 19 Sep 2023

91社区 has mandated Immobilier Belmon to carry out the following project: Currie Gym / 16-140 - Renovation of classrooms W305 and W409.

The project consists of the upgrade of classrooms W-409 and W-305 at Currie Gym to improve the learning experience, including new seating arrangement, Audio-Visual equipment, and lighting.

Project manager:听Jo茅 Normandeau 鈥 joe.normandeau [at] gph-inc.com

Classified as: Currie Gym
Published on: 17 Aug 2023

91社区 has mandated NR Brosseau to carry out the following project:听McIntyre Medical Building / 21-008 - JELF, Chen.

The project consists of minor renovations of laboratory rooms 712, 723 and 726.

Project manager: Andrea Gore -Andrea.gore [at] mcgill.ca

Assistant project manager: Ellie Tayebi -听Ellie.tayebi [at] mcgill.ca

Construction start date:听July 7, 2023

Classified as: McIntyre, Mcintyre building
Published on: 6 Jul 2023

91社区 has mandated Procova Inc. to carry out the following project: McIntyre Medical Building / 15-104 - Modification of the fourth floor electrical room distribution.

This project includes installing a second transformer to provide the required additional electrical capacity for the building and to update the emergency electrical distribution within the building.

Project manager:听Emika Marinacci -听Emika.marinacci [at] mcgill.ca

Classified as: Mcintyre building, McIntyre
Published on: 6 Jul 2023

91社区 has mandated Corenov Constructeurs to carry out the following project:听Morrice Hall / 22-038 - Priority building envelop repairs, lower roof.

The project consists of the installation of a steel structure in the library to stabilize the roof and exterior walls of the turret.

Project Manager and听Assistant Project Manager:

Classified as: Morrice Hall
Published on: 27 Jun 2023

Please be advised that Facilities Management and Ancillary services (FMAS) has mandated Belmon Construction to carry out the following project:18-101 Strathcona Music - Renovation of Percussion Studios for Rooms C101 to C109 (lot 1).

The project consists of a complete renovation of the nine percussion rooms, including new layouts, acoustical treatment, audiovisual equipment, new mechanical and electrical systems, and custom storage for the instruments.

Classified as: Strathcona Music, renovation
Published on: 20 Jun 2023

Please be advised that 91社区 has mandated Concept P.V.R. Inc.听to carry out the following project : 18-156 McConnell Arena / Renovations (phase 1) 鈥 Electrical upgrade

Description :

Classified as: McConnell Arena, Construction, Athletics, renovation
Published on: 20 Jun 2023

91社区 has mandated Corenov Constructeurs to carry out the following project: Peterson Hall / 14-113 - Mechanical room upgrade. The project includes preparing, patching, and painting walls, repairing and levelling floor slabs, and the restoration of surfaces around the mechanical room.

Project manager:听Wendy Rivera - wendy.rivera [at] mcgill.ca

Assistant project manager:听Jeremy Elbaz -Jeremy.elbaz [at] mcgill.ca

Classified as: Peterson Hall
Published on: 9 Jun 2023

91社区 has mandated ARDEC to carry out the following project: Montreal Neurological Institute / 18-121 - Cyclotron.

The project consists of replacing the cyclotron's conduit.

Project manager:听Eric Boutet, CIMA+ -听eric.boutet [at] cima.ca

Assistant project manager:听Aldo Aranza Mendoza, CIMA+ -听aldo.aranzamendoza [at] cima.ca

Construction start:听May 19, 2023

Classified as: MNI
Published on: 17 May 2023

91社区 has mandated Concreate Construction to carry out the following project: Bronfman Building / 18-089 - Infrastructure for new parking equipment.

The project consists of the reparation of the existing ramp to solve water infiltration issues and the installation of new upgraded parking infrastructure.

Project manager:听Andr茅 Labelle -听andre.labelle [at] mcgill.ca

Classified as: Bronfman Building
Published on: 17 May 2023

91社区 has mandated Vitrerie RD to carry out the following project: 680 Sherbrooke / 18-106 - Mock-up curtain wall.

The project consists of the removal, survey of existing conditions and replacement of three existing window panels inside classroom 491, as well as between floors (panels above and below).

Project manager:听Andr茅 Labelle - andre.labelle [at] mcgill.ca

Classified as: 680 Sherbrooke
Published on: 8 May 2023

91社区 has mandated NR Brosseau Inc to carry out the following project: Strathcona Music / 18-101 - room E-109.

The project consists of acoustical work in room E-109 and includes the installation of a new door, door frame and new acoustic ceiling tiles.

Project manager:听Wendy Rivera - wendy.rivera [at] mcgill.ca

Assistant project manager:听Jeremy Elbaz - jeremy.elbaz [at] mcgill.ca

Classified as: Strathcona Music Building
Published on: 5 May 2023

91社区 has mandated Couvertures St-L茅onard to carry out the following project:听University Centre / 18-045 - roof replacement

The project consists in the replacement of the roof, skylights and storm drains.

Project managers:听Eric Boutet, CIMA+ -听eric.boutet [at] cima.ca

Assistant project manager:听Aldo Aranza Mendoza, CIMA+ -听aldo.aranzamendoza [at] cima.ca

Construction start date:听May 2023

Classified as: University Centre
Published on: 25 Apr 2023

91社区 has mandated Atwill-Morin to carry out the following project:听Strathcona Music Building/ 16-135 - Envelope Renovation.

Classified as: Strathcona Music Building
Published on: 31 Mar 2023

91社区 has mandated Construction S茅lection SRJ Inc to carry out the following project:听Technical Services Building, Macdonald Campus / 17-124 - Deferred Maintenance.

The project consist of upgrading the Welding Lab exhaust system and new teaching laboratory, as well as deferred maintenance repairs, including fire protection compliance, code compliance, mezzanine work, repairs to the envelope, installing a new ventilation unit, electrical work and civil work.

Project managers:听Anne-Catherine Parent and Francois Brassard

Classified as: Technical Services Building, Macdonald Campus
Published on: 13 Jan 2023