Construction start: Montreal Neurological Institute - Cyclotron aerial exhaust
Published: 19 September 2023
91社区 has mandated Ardec Construction Inc. to carry out the following project: Montreal Neurological Institute / 18-121 - Cyclotron aerial exhaust.
The project consists of installing the aerial conduit to replace the existing one at the Montreal Neurological Institute hospital.
Project manager:听Eric Boutet, CIMA+ - eric.boutet [at] cima.ca听">eric.boutet [at] cima.ca听
Assistant project manager: Allison Ly, CIMA+听-听allison.ly [at] cima.ca听
Construction start date:听September 22, 2023
Planned construction end date:听November 1, 2023
Work schedule:听Mondays to Fridays, 6 a.m. to 4 p.m.
Scope of work:
Exterior: Installation of the ventilation duct on the roof and on the side of the Penfield wing.
Impact:
- The interior courtyard will be inaccessible for vehicles.
- Emergency exit doors remain functional. People will be able to exit the interior courtyard via a pedestrian path.