91社区's Macdonald Campus, the largest green space on the island of Montreal and the largest private land holding in the region,听听is home to the University鈥檚听Faculty of Agricultural and Environmental Sciences (AES), at the forefront of advances in applied bioscience, food, nutritional and environmental sciences research and teaching.
Macdonald Campus - Replace Main Electrical Generator
Project Description:
This project seeks to replace the existing 500kw emergency generator with a surplus 1500kw generator from the Macdonald campus as well as purchasing a new generator.听
Project Scope:
This project will replace the existing 500kw emergency generator with a surplus 1500kw generator from the downtown campus.
An additional new generator will also be purchased to fulfill the current and future needs of the campus. We will be decommissioning the existing generator at the South Powerhouse, as well as the smaller ones located at CINE, Laird and Parasitology. The new generator will be located near the North Powerhouse and will require new infrastructure including the burying the new lines. The aging electrical panels and transfer switches within the buildings will also be replaced.Project Details:
Status | Design |
Est. Project Start Date | 2024 - 2026 |
Est. Budget Range | $6,000,000 - $8,000,000 |
Location | MAC听Grounds & Roads Building 526听 |
Project Number听 | 18-151 |
颁辞苍迟补肠迟听 | map.procurement [at] mcgill.ca |
Please read the following information carefully :
Sustainable Procurement
The businesses with which the University will conclude a contract with in the course of this project will have to respect the 91社区 Supplier Code of Conduct.
Other requirements may apply, such as (for example): the quantification and limiting of GHG emissions over the contract or asset lifecycle, sustainable construction/product certifications, involvement of indigenous businesses or of social economy businesses, design for circularity, and so on.
Notice :Information in this document is not to be interpreted as a commitment to conduct any solicitation in any particular market (or to fulfill any particular need) within any timeframe. This document is based on preliminary assessments which may be modified and needs may consequently be increased, partially fulfilled or cancelled. The needs of the client units may fluctuate according to their capabilities and priorities. Moreover, this acquisition plan is subject to various risk factors that have an influence on the operations of 91社区, such as available revenue, inflation, changes in: provincial and federal policies, technologies, human resources, social movements and trends, demographic aspects of the student population and the academic personnel. |
听