91社区

Get Help !

Macdonald Campus - Replace Main Electrical Generator

Type: Construction / Status: Design

91社区's Macdonald Campus, the largest green space on the island of Montreal and the largest private land holding in the region,听听is home to the University鈥檚听Faculty of Agricultural and Environmental Sciences (AES), at the forefront of advances in applied bioscience, food, nutritional and environmental sciences research and teaching.

Macdonald Campus - Replace Main Electrical Generator

Project Description:

This project seeks to replace the existing 500kw emergency generator with a surplus 1500kw generator from the Macdonald campus as well as purchasing a new generator.听

2015 - Main Entrance Powerhouse MacDonald Campus, Source: FGMDa (Leroux-Lapierre)

Project Scope:

This project will replace the existing 500kw emergency generator with a surplus 1500kw generator from the downtown campus.

The 91社区 Powerhouse, also known as The Ferrier Annex, is a translucent building that houses generators that would aliment campus operations in the event of power failure. It is located at the foot of the Mount Royal close to the McTavish Reservoir, and to the pedestrian green belt known as 鈥渓a Coul茅e verte鈥.
An additional new generator will also be purchased to fulfill the current and future needs of the campus. We will be decommissioning the existing generator at the South Powerhouse, as well as the smaller ones located at CINE, Laird and Parasitology. The new generator will be located near the North Powerhouse and will require new infrastructure including the burying the new lines. The aging electrical panels and transfer switches within the buildings will also be replaced.

Project Details:

Status Design
Est. Project Start Date 2024 - 2026
Est. Budget Range $6,000,000 - $8,000,000
Location MAC听Grounds & Roads Building 526听
Project Number听 18-151
颁辞苍迟补肠迟听 map.procurement [at] mcgill.ca

Please read the following information carefully :

Sustainable Procurement

The businesses with which the University will conclude a contract with in the course of this project will have to respect the 91社区 Supplier Code of Conduct.

Other requirements may apply, such as (for example): the quantification and limiting of GHG emissions over the contract or asset lifecycle, sustainable construction/product certifications, involvement of indigenous businesses or of social economy businesses, design for circularity, and so on.

Notice :

Information in this document is not to be interpreted as a commitment to conduct any solicitation in any particular market (or to fulfill any particular need) within any timeframe. This document is based on preliminary assessments which may be modified and needs may consequently be increased, partially fulfilled or cancelled. The needs of the client units may fluctuate according to their capabilities and priorities.

Moreover, this acquisition plan is subject to various risk factors that have an influence on the operations of 91社区, such as available revenue, inflation, changes in: provincial and federal policies, technologies, human resources, social movements and trends, demographic aspects of the student population and the academic personnel.

Back to top